integratedAIR was appointed to design and implement a
complete upgrade of an ageing scrap extraction and baler feed system within a
high-output can manufacturing facility. The existing system was over 30 years
old and no longer capable of supporting the site’s operational demands.
The project required the full strip-out of the existing
scrap system, installation of new air separators, ductwork, platforms, and
controls, and preparation for the integration of two new balers, all within a
strictly limited factory shutdown period.
The integratedAIR team was on site two weeks
before the factory shutdown. During this phase, the team made extensive
preparations so that once the shutdown began, all activities could be carried
out swiftly.
The team carried out detailed site surveys and finalised the
installation sequence at an early stage. Opportunities were identified to
fabricate, assemble, and prepare essential elements in advance, including
exhaust fans, silencers, and control panel components. Wherever possible,
sections of the system were built off-site, with crane lifts planned in detail
to minimise on-site installation time. This meticulous preparation meant that
once the shutdown began, all activities could progress without delay.
Once the factory entered shutdown, integratedAIR mobilised
immediately. The baler area's roof was temporarily removed. During the shutdown
period, integratedAIR carried out the full strip-out of the existing scrap
system, excluding the balers, and installed a new mezzanine platform supported
by a complete structural design. The works included installing two air
separators, one with provision for a future whole
can, along with new ductwork, exhaust air ducting, and associated
supports.
New roof-mounted silencers were installed, supported by
structural upgrades to accommodate the additional load. All associated controls
for the weigh hopper, new exhaust fans, and trimmer fan were wired and
commissioned as part of the shutdown works.
The design engineers effort was particularly noteworthy,
ensuring that all equipment fit together within the confined baler room while
still allowing for future expansion.
An external specialist
contractor carried out the physical installation. Due to their position at the
base of the scrap handling process, the balers and all associated equipment had
to be fully installed before integratedAIR could complete the final scrap system
works.
This sequencing was critical, as the scrap extraction system
needed to be designed and configured around the balers to ensure correct
alignment, airflow, and material flow. Once the balers and related equipment
were in place, integratedAIR completed the integration and commissioning
process, ensuring the balers operated correctly in line with the upgraded scrap
system and performed as intended within the modified installation.